Lee’s Summit Community Christian High School Phase I

1500 S.W. Jefferson
Lee’s Summit, Missouri

GMK Architects with HGK Construction
Management is providing full Architectural/
Engineering Design, programming, planning,
and Construction Management services for this
new high school.

The 106,500 sq. ft. facility designed to be built
In three phases includes:

• Administrative Area
• Science Rooms
• Kitchen/Cafeteria
• 7-12 Grade Classrooms
• Locker Rooms
• Training Area
• 2nd Floor Classrooms

Phase I is 45,000 sq. ft.

Phase I – Construction started January 2006
Construction completed January 2007

Phase I – Construction cost $6,300,000